Hodson Science & Technology Renovations
September 30 Updates
- Salvaged cabinetry with temporary top installs in 308C and 121 have progressed.
- Power and data in have been relocated. Install continue to be coordinated around class activities.
- New CAT6 data has been pulled in the 3rd floor suite.
- Continuing with framing
- Walls have been cut out as needed for blocking to be installed for cabinetry.
- Scientific casework has been reviewed and should be released this week for fabrication.
- Mechanical Duct install has begun.
September 28 Updates
- Duct install
- Prep work needed for duct connection to existing main duct outside of the suite. This will require the cutting out of the bulkhead just outside the doors of the suite. (Diagram of area below)
- Hayes will have a plastic enclosure around this work area to prevent dust migration and the cutting out of the ceiling will occur prior to 8:15am during the noisy work hours.
- Prep work needed for duct connection to existing main duct outside of the suite. This will require the cutting out of the bulkhead just outside the doors of the suite. (Diagram of area below)
- Work will continue in 308C, 005 and 121.
September 21 Updates
- Activities will be the same level of noise and activities as the past week.
- Framing will continue.
- Work will continue 308C, 005 and 121.
Other Updates:
- Lewis Contractors who will be working on the envelope improvements and some of the main building mechanical improvements were onsite on Friday the 19th with a Mechanical contractor for a survey.
September 2 Updates
- Hayes Construction will be on site starting around 7 a.m. on September 8. Activities will include putting construction protection in place and starting to prep for Demolition.
- September 9: Demolition contractor will be onsite; dumpster may be dropped as early as today. Please note: the dumpster is for use by the contractors only. Other usage is prohibited and could create slowdowns in construction process and added costs.
- Phase 1- Envelope work and misc.
- No anticipated construction activities for the month of September
- Hodson Annex
- Finalizing schedule for design with design team.
July 28 Update
- No new updates
July 11 Update
- IT has started the computer relocation from Hodson Annex.
- Computers from Hodson 237 have been moved to Hodson 235.
- Hodson Annex Cyber Security will be relocated to Hodson 237.
- Changes being made in AdAstra
- The permit has been submitted for the 3rd floor suite renovation (pre-bid meeting week of July 14)
- Lewis Contractors has been selected as construction manager for the exterior improvements and annex renovation (kick-off meeting week of July 14)